Robin Drive/Court Drainage Improvements

Print
Press Enter to show all options, press Tab go to next option

 

Robin Drive and Court Drainage Project Aerial Map

Location:

Robin Drive and Robin Court (Click Here to see an interactive GIS Map, or click the image above to download a closeup PDF of the project)

Approximate Start Date:

January 2014

Approximate End Date:

November 2014

Purpose:

To improve drainage capacity underground and overland on Robin Drive and Robin Court to mitigate flooding of homes on Robin Court

End Result:
  • Drainage improvements along Robin Drive and Robin Court, including pipes, concrete flumes and inlets 
  • Updated water lines for all properties associated with the project
  • A repaved road, once drainage construction is complete
Estimated Construction Cost:

$622,429

Funding Source:

City of Keller, out of the Drainage Utility Fund 

Progress:

PROJECT COMPLETED 

Closures/Detours:

NONE

For more information about this project, contact Keller Public Works at 817-743-4080 or publicworks@cityofkeller.com.